Automation Schedule (SM205030) has its Next Execution Date going into the past
When an Automation Schedule (SM205030) runs longer than its next execution time, its Next Execution Date goes into the past
Date: 16/08/2023
Status: Fixed in 2025R2
Reference: ADV-50249
Issue
Automation Schedule (SM205030) has its Next Execution Date going into the past
Workaround
If you no longer need an automation schedule that causes errors, you can simply delete it or deactivate it on the Automation Schedules form (SM205020)
If you do still need the automation schedule, ensure the next execution date is set in the future and does not overlap with any other schedules. For further information refer to Optimising automation schedules